World-first wind turbine tech puts an 8-megawatt charger on an oil rig

Mon, 16 Sep 2024 04:45:01 +1000

Andrew Pam <xanni [at] glasswings.com.au>

Andrew Pam
https://newatlas.com/energy/parkwind-offshore-charging-station/

"In the Belgian North Sea, maintenance vessels are now able to tether to an
automatic cable at a wind farm to get their batteries topped up. The innovative
system is the first of its kind and a major step in keeping electric vessels as
green as possible.

The charging system was deployed at Belgian's Nobelwind wind farm, which has
been in operation since 2017 and features 50 turbines covering 19.8 square km
(7.6 square miles) at sea. The facility is the third deployed by the Parkwind
company and it supplies power to about 190,000 households.

Nobelwind's new charging station was shipped on a crew transfer vessel (CTV) 47
km (29 miles) offshore and its modular components were raised amongst the
sea-based wind turbines using the facility's substation crane. Once it was
established, the company successfully used it to charge up one of its CTVs.
Parkwind reports that the transfer went off without a hitch, with no disruption
to the facility's operation.

As you can see in the following video, which shows the system being tested with
a land-based module earlier this year, the entire process is fully automated
with no need for crew members to either connect or disconnect the charging
tether, an innovation that adds to the system's safety factor."

https://www.youtube.com/watch?v=outjr8nct4U

Via What Could Go Right? Every Second Counts
https://theprogressnetwork.org/public-warning-systems/

Share and enjoy,
               *** Xanni ***
--
mailto:xanni@xanadu.net               Andrew Pam
http://xanadu.com.au/                 Chief Scientist, Xanadu
https://glasswings.com.au/            Partner, Glass Wings
https://sericyb.com.au/               Manager, Serious Cybernetics

Comment via email

Home E-Mail Sponsors Index Search About Us